With a lead time of just three days from order to delivery, including confirmation of quantities, this project was always out to prove the point that Beco WALLFORM is a rapid method of construction.
Onsite: One pair, semi-detached bungalows
• Day 1 – Delivery, erect formwork and concrete substructure.
• Days 2 & 3 – Backfill, compact, construct solid floor slab.
• Day 4 – Erect & concrete external and party walls to half height.
• Day 5 – Erect & concrete external and party walls to roof level and install wallplate.
Quick to construct and, with a good basic U-value (0.18 W/m²K), built-in airtightness and minimal thermal bridging already achieved, following activities continue without distraction.
DESIGN: AA Design Ltd
CONSTRUCTION: Bramall Construction