Borve – The Wallforming Begins!

Another delivery of BecoWallform was securely loaded and dispatched from our warehouse.

This full trailer headed up to Borve, on the Isle of Barra, courtesy of our regular, local haulier John Reid Trucking.

Once delivered, the Wallform blocks are quickly assembled ready for concreting up to dpc level.

IMG_20150520_121752Borve pipework in place


The substructure walls completed, two levels of floor insulation are laid with staggered joints to prevent thermal bridging.

Concrete slab now laid over the insulation, provides a working platform for the main Wallform construction.

11400980_643227409112754_8741417657227653290_n-001

Borve slab

Next Update: Construction
Borve – The Wallforming Begins! was last modified: December 5th, 2017 by Beco